TUESDAY, MARCH 19

8-8:25

City of Lubbock uses Sliplining to Rehab 24-Inch Supply Line under Major Thoroughfare
Speakers: Kyle Wroblewski & Shawn Garcia, Underground Solutions

Gain insights into the evaluation process for rehabilitation methods, as well as a discussion of trenchless technology options available for waterlines. Learn about the complex challenges faced in an urban environment, construction and engineering design considerations, and knowledge about rehabilitation methods.

8:30-8:55

Design-Build Approach Delivers Cost Savings, Simplified Construction for Dallas Water Utilities
Speakers: Tracey Long, Hazen and Sawyer; Rishi Bhattarai and Rakesh Chaubey, Dallas Water Utilities

Learn how design-build provided a single point of responsibility for the 96” interceptor tunneling project; time savings, as construction could begin before the design was complete; and determination of costs early in the process, giving DWU the opportunity to maximize the length of interceptor constructed.

9-9:25

Creation of the Pipeline Assessment & Certification Program (PACP)
Speaker: Rod Thornhill, White Rock Consultants

Learn about other technical advancements that set the stage for PACP and gain new ideas for collaboration by utilities nationwide for the common benefit of the wastewater collection system industry.